Hi all,
please can U advice how to set SS with a lag and FF simultanously in MS Project?
I have 3 tasks: A, B, C
Task B starts N days before A and ends the day C ends.
Sample:
Task A = development
Task B = development environment preparation & support
Task C = UAT (user acceptance tests)
Task B needs to start with environment preparation at least 30 days before development will start (Task A SS-30d) and to finish together with UAT (Task C FF).
I found an existing discussion ===> SS and FF simultaneously with a solution described here ===>
http://support.microsoft.com/kb/141733 (Hammock task) but in addition to this I need to start the task N days earlier.
Please does exist an elegant solution for this?
Thank you, Dag.