Usually, the primary difference between % Complete and % Work Complete is that % Complete is calculated based on Duration values while % Work Complete, as the name suggests, is calculated based on the value for Work. Below are the formulas for calculating the two values:
%Complete = (Actual Duration/Duration)*100
%Work Complete = (Actual Work/Work)*100