Hope someone can help, because my IT manager claims my problems stem from the Rag formula I'm using.
Basically, my problem arose when I took the 9 projects I managed all linked to a resource pool and moved them to a new spot on our server. After moving them I unlinked each file to the existing resource pool and created a new resource pool. Then I linked each project to this new resource pool and created a master project file with all 9 projects. Once this master was created I noticed that tasks within each project file were being duplicated and some tasks from one project file showed up on another project file. In other words, Project A had duplicated tasks and Project C tasks showed up in Project B. However, these occurances only happened within the master project file and not in each individual project file when opened independent of the master file. Also, in one of my weekly meetings, when reviewing a project file using our projector equipment, the Rag column would not completely display. Some Rag bullets were not showing, but an error showed in its place, when I removed the projector everything worked correctly again.
You should also note, that each file has a custom calendar and has been baselined a number of times. I've never seen this happen before using a master, so I'm wondering if Rag formulas are unique to software versions - remember I'm using 2007 (not server). Also, none of these problems started happening until after I moved all these files to another part of our server. I provided the Rag below:
Rag Formula (Number Field)
IIf([% Work Complete]=100,10000,DateValue([Finish])-DateValue([Current Date]))
Graphical
Is greater than or equal to 10,000 Blue
Is greater than or equal to 30 Dark Green
Is greater than or equal to 6 Light Green
Is greater than or equal to 0 Yellow
Is less than or equal to (1) Red
Thanks for.
Bookmarks