I have inherited a programme plan and the first thing I need to do is re organise the plan. I am having problems when moving tasks to different locations in the plan, ie to under a different project. The first issue is that dependencies are being lost and the second is that dates are being changed seemingly randomly. Is there any advice that you can give to rectify this. As you may be able to tell I am fairly new to MS Project