I have a schedule that is several 1000 lines long. For one period (sea trials), I have 10 tasks that must happen which then means that the rest of the other tasks cannot happen. The schedule has several different calendars because of different contractors working hours. I put the 10 day duration for the sea trials period in the standard calendar which then extends any tasks that go though sea trials by the according amount. The problem I have is that is also blocks out the period that I need to do the 10 tasks which are sea trials task. I need these 10 task to be shown through the non working time. I have tried creating a new calendar and made sure that these sea trials task are working time but it still does not work
Does anyone have any idea if this can be done.
Short question: Can I make task work in a non working time period?