    sad setup task in project 2007, need help!!

    Hello forum, new member here and I have a question that has been bothering me when creating project that I hope some here can assist...

    I'm currently creating a project in PWA using MS Project 2007, now the task will extend across 3 weeks, the resource will be allocated 50% to the task, however the total amount of hours the task is going to take is 30 hours (Standard calendar)

    Now if I make the task be the time is should be (3 weeks) the total amount of hours for the task go up dramatically, if I shorten the length of the task then I don't I loose the real date of when the task will be completed, which then creates an issue to link to another task....

    Hope you can understand my dilemma......thank you!

  2. #2
    Join Date
    Dec 2007
    Posts
    1,599

    Re: setup task in project 2007, need help!!

    When inserting a task among linked tasks, you can have a new task linked automatically or not link it at all.

    • To link the new task, click the task that you want the new task to precede, and then click New Task on the Insert menu.
      • Note If this doesn't work, on the Tools menu, click Options, and then click the Schedule tab. Make sure that the Autolink inserted or moved tasks check box is selected.

    • To add the new task without linking it, click the task with which the new task will occur concurrently, and then drag to create the new task in a blank portion of the Network Diagram.

  3. #3
    Join Date
    Feb 2011
    Location
    South Florida
    Posts
    2

    Re: setup task in project 2007, need help!!

    Quote Originally Posted by expertz View Post
    When inserting a task among linked tasks, you can have a new task linked automatically or not link it at all.

    • To link the new task, click the task that you want the new task to precede, and then click New Task on the Insert menu.
      • Note If this doesn't work, on the Tools menu, click Options, and then click the Schedule tab. Make sure that the Autolink inserted or moved tasks check box is selected.

    • To add the new task without linking it, click the task with which the new task will occur concurrently, and then drag to create the new task in a blank portion of the Network Diagram.
    thanks for your reply, but the linking is not the issue.....is the length of the task versus the amount of hours it displayes.......but I try a couple of things and I think I got. Basically, to ensure the amount of hours remaing the same I just play with the % the resource is allocated.....

Similar Threads

  1. Replies: 4
    Last Post: 20-04-2012, 11:22 PM
  2. ms project task resource setup
    By clive83 in forum Windows Software
    Replies: 1
    Last Post: 24-03-2012, 08:57 PM
  3. Brewery Task Lengths for Project 2007
    By MrMatlock in forum Windows Software
    Replies: 1
    Last Post: 21-05-2011, 05:57 AM
  4. Ms Project 2007 Task setup
    By Mr Karlsson in forum Windows Software
    Replies: 1
    Last Post: 30-04-2011, 01:45 AM
  5. Project Professional 2007 task duration
    By iShree in forum Microsoft Project
    Replies: 3
    Last Post: 04-08-2009, 06:24 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,750,133,460.88995 seconds with 16 queries