Although experienced in Project for normal work hours, I am having a devil of a time figuring out how to set up a schedule for a 24/7 training program. Selected the 24hour format but then Durations ended up three times what was expected. So, went into the Timescale and defined a day as 24 hours but then ended up with Durations that show as fractions/decimals of a day? Any experience with this? Thanks, Mike