I am trying to set weighted milestones within a MS Project 2003 schedule. For example, Construction is the summary level and the sub-tasks below are
- 35% recognized when Subcontractor Bid Complete
- 35% recognized when Phase 1 Site Prep complete
- 28% recognized when Phase 2 Final Wiring, bollards complete
- 2% recognized when disposal and cleanup is complete
After all 4 have been completed then "Construction" is 100% complete.
Does anyone know how to set this up in MS Project 2003? Do you have a script or VBA that could be used?
Your assistance in this is appreciated.