    Unique ID in MS Project?

    Hello,

    I am trying to figure out a way to create unique ID's in a MS project, which serves as a subprojects.

    For an example:

    In project one I create an activity with ID 123.
    This project is one out of four subprojects.
    If I would open any of the other three, there must not exist another 123.

    Is this possible or am I doing it all wrong and need to rethink?

    /Sudden

  2. #2
    Join Date
    Dec 2007
    Posts
    2,288

Similar Threads

  1. Replies: 4
    Last Post: 20-04-2012, 11:22 PM
  2. Replies: 3
    Last Post: 10-11-2010, 07:27 PM
  3. Replies: 1
    Last Post: 20-08-2010, 01:27 AM
  4. How do I convert Project 2007 document to open in Project 2003?
    By nehal_serpa in forum Microsoft Project
    Replies: 6
    Last Post: 31-10-2007, 03:12 AM
  5. Project 2007 Client Cannot Connect To Project Server 2003
    By PARRISH in forum Microsoft Project
    Replies: 1
    Last Post: 21-02-2007, 10:24 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,728,644,867.09895 seconds with 16 queries