Thread: Project 2003 - piecework rates

  1. #1
    Join Date
    Feb 2011
    Posts
    2

    Project 2003 - piecework rates

    New to MS Project (2003) so maybe this is a basic question. I don't wish to use days to work out how long a resource takes to complete a task but would like to use areas and lengths. For example a farmer ploughs 3 hectares in a day. How would I alter the settings in Project to do this?

  2. #2
    Join Date
    Jan 2006
    Posts
    605

    Re: Project 2003 - piecework rates

    You can try to input the Start date & set the duration to 1 day, you will have your finish date on the same day at 5PM. Go to tool- options- view, change the date format to show the time, e.g "February 5 2011, 12:32". You can see the start & finish time of the same activity on the same day.

  3. #3
    Join Date
    Feb 2011
    Posts
    2

    Re: Project 2003 - piecework rates

    Not quite what I was wanting. Using the farmer analogy where he ploughs 3 hectares in a day I would like to input the area for him to plough, say 9 hectares so that the prog can tell me it would take 3 days to do the work. How does one do that?

Similar Threads

  1. Replies: 4
    Last Post: 26-03-2012, 06:42 PM
  2. Replies: 1
    Last Post: 20-08-2010, 01:27 AM
  3. Error on importing project in MS-Project 2003
    By fredpaquet in forum Windows Software
    Replies: 4
    Last Post: 24-04-2009, 05:06 AM
  4. How do I convert Project 2007 document to open in Project 2003?
    By nehal_serpa in forum Microsoft Project
    Replies: 6
    Last Post: 31-10-2007, 03:12 AM
  5. Project 2007 Client Cannot Connect To Project Server 2003
    By PARRISH in forum Microsoft Project
    Replies: 1
    Last Post: 21-02-2007, 10:24 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,750,252,712.93574 seconds with 16 queries