I have a project plan with over 1000 lines (that I inherited) and whenever I open it up, I get the following message - "No calculations can be performed. There is a circular relationship in task 729 Bug fix testing of 'Rainier Phase 1'. The successors of this task refer back to this task or its predecessors, causing a circular reference. To remove the link that is causing the circular reference, select the two tasks that are causing the circular link, and then click Unlink Tasks on the Task tab."I have looked at task 729 and see nothing wrong. I don't even know where to find "Rainier Phase 1".
So here are my questions:
How do I find if there is any other task in the project plan pointing to task 729 (I used Find and found nothing). I need to get rid of this circular link because it is causing the plan to not calculate any % complete as I update it, and it is not letting me add tasks and indent/outdent them without giving me another error message that tells me if I do that it will create a circular relationship (which it won't).
So my plan is stuck in the water. Any help would be greatly appreciated.
Thanks,
Tim
Bookmarks