Hi everyone,
I`ve created a project in MS Project 2003 and later went on in MS Project 2007. After this conversion I wanted to display my progressline. This created a completely straight vertical line . So I investigated what was wrong. I copied the data from the baseline into startdate1/enddate1 and after this I copied the data back into the baseline-colomns. This created a baseline, but an incorrect one. These are the symptoms:
- some tasks that are not finished will display it`s progress at 100% of the baseline
- some tasks that nog have started yet, do show progress on the baseline
(I`ve added an example of this situation in the attachment)
The only way I get a correct progressline so far is to re-create the baseline, one line at a time (I`ve got a project of 3000 lines, so ).
Can you help me identify the problem and possibly have the solution for me? I`d be very grateful
Bookmarks