I have a task that always finishes on a Wednesday. So if I have a task where the actual work is 4 days, so if were to start on Monday of a given week it would be complete by lets say Thursday of the same week, all things of course being equal, the problem is even though resources a freed formal sign-off cannot occur until the first Wednesday after the work.
So whether that tasks takes 2 days, 4 days or 144 days the finsh date is always Wednesday.
Does anyone know how to set a task up so it always finishes on a Wednesday?