SOS. I am using MS-project 2003 professionial edition - when i link tasks, the second task should move its start date to the completion of task 1 start date and it doesn't - please help (it has nothing to do with fixed tasks or durations)
What I start with:
Task 1, duration 2days, (default) start date Jan 1, 2011
Task 2, duration 1 day, (default) start date Jan 1, 2011
What I expected:
When i link task 2, to task 1, using a finish-start dependency, task 2 should automajically show a start date of Jan 3 as shown below (But it DOESN'T):
Task 2, duration 1 day, (default) start date Jan 3, 2011
What is incorrectly displayed:
Instead it shows a link, but, it appears to be a start start link (even though i confirmed it was a finish start link). Here's what i get after linking:
Task 2, duration 1 day, (default) start date Jan 1, 2011
Can you please help me??
Sad and sorry.