Just wondering if someone can help me with a problem I'm having.
I'm relatively new to MS Project and am having fun trying to set up a project plan!
Basically I have a milestone date for a task group which is the initial set up date of a program.
At various timepoints from this initial date I have tasks to do...
e.g. 1 month, 3 month, 6 month, 9 month and 12 month.
I was intending on setting these tasks as sub tasks of the main task. I want these to start at 1 calendar month after the milestone, 3 calendar months after the initial milestone etc
(So if the milestone was 1st Jan 2012, I want the first task to be 1 month - the 1st of Feb 2012 - or the nearest working day to that)
However, the duration of these sub tasks are in days (e.g. 10 or 15 days) but I want the duration to be working days not calendar days (which in my case is Monday - Friday and I have also set up my calendar to include all public holidays and non-working days)
Is this possible?
Thanks in advance