    Project 2007 - Custom working hours

    I am trying to set up custom working hours which are shift hours.

    Project doesn't let me change to the following non standard working hours:

    6.30PM to 10.30PM (line 1)
    11pm to 3:30AM (line 2)

    Error says the end of the shift should be later than the start - which I understand because Project can only schedule hours in the same 12hr period.

    But is there a work around for this to show the shift ACTUALLY starts at 6.30PM on Day 1 but finished at 3:30AM on Day 2?

  2. #2
    Join Date
    Dec 2007
    Posts
    1,736

    Re: Project 2007 - Custom working hours

    If the start time for the task is set to the default of 8am for 9/1 then can you try to change the format and change the start time to 12:00 am, this way everything would be alligned the way it was supposed to.

Similar Threads

  1. Custom Field to display start time in Hours and Minutes
    By LaalaManii in forum Microsoft Project
    Replies: 4
    Last Post: 20-04-2012, 08:02 PM
  2. Project start date shows in hours
    By ofiramitai in forum Microsoft Project
    Replies: 6
    Last Post: 20-02-2012, 07:19 PM
  3. Project 2007 Non Working Time Exceptions
    By waffey in forum Windows Software
    Replies: 1
    Last Post: 17-09-2011, 12:32 PM
  4. Changing effort hours in project into days and vice versa
    By aglobal in forum Windows Software
    Replies: 1
    Last Post: 20-04-2011, 06:09 PM
  5. Project Duration measured in hours and minutes
    By Kuval in forum Microsoft Project
    Replies: 2
    Last Post: 09-10-2009, 02:22 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,711,672,746.75858 seconds with 17 queries