I have set up a project with tasks and sub tasks, I am starting to enter in duration and starting dates and linking tasks. the first group of tasks I have done the first 3 have duration of .5days, 0days, .5days, but it is throwing the the start and finish dates out by a day, I have checked that it is a working day.
Scope Audit 0.5 daysFri 19/11/10Fri 19/11/10 0%
Intent To Audit Notification 0 daysFri 19/11/10Fri 19/11/10 0% 1598
Audit Preperation 0.5 daysTue 23/11/10Tue 23/11/10 0% 1599
Desk Top Audit 1 dayTue 23/11/10Wed 24/11/10 0% 1600