Thread: MSP Task Relationship Update Query

  1. #1
    Join Date
    Oct 2010
    Posts
    2

    MSP Task Relationship Update Query

    Hi,
    Can any one advise how MSP 2003 handles the progressing of task relationship updates in particular SS and FF with durations.
    Are they updated automatically as task % increases or do you have to update manually??
    I intend to update the schedule on a weekly basis

    Thanks, JD

  2. #2
    Join Date
    May 2008
    Posts
    255

    Re: MSP Task Relationship Update Query

    Microsoft Project permits constraints to be allocated to tasks, such as "start no later than", "must finish on" etc. There are 8 limit types and for each constraint type you must enter a date. In general they should be relevant only where obligatory so that MSP can be free to analyze task start and finish dates etc. Each time you enter a constraint you inflict restrictions on MSP. If you want to know more about the MSP Task Relationship, you can check it at http://www.ami.ac.uk/courses/ami4040_pmme/unit_02/#sec2.

Similar Threads

  1. Data Mining Query task in SQL Server 2008
    By Elijah2010 in forum Software Development
    Replies: 5
    Last Post: 23-02-2010, 05:33 AM
  2. Update query not working properly in asp.net
    By Linoo in forum Software Development
    Replies: 4
    Last Post: 19-01-2010, 09:43 PM
  3. Hibernate dynamic update query
    By GianCarlo in forum Software Development
    Replies: 3
    Last Post: 01-08-2009, 08:47 PM
  4. SQL query between 2 tables linked by many to many relationship
    By Luis234 in forum Software Development
    Replies: 2
    Last Post: 09-05-2009, 02:17 PM
  5. MySQL UPDATE Query
    By ANDERS in forum Software Development
    Replies: 2
    Last Post: 10-02-2009, 11:57 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,714,006,270.10923 seconds with 17 queries