Hi everyone,
I use ms project 2007 at work. I need to set up the program with a target: I enter an activity with an end constraint and I assign a resource with a uniform distribution. I'd like that when I introduce the effective work of this resource in the timesheet, the remaining work will been automatically distribute until the end constraint. Instead it is been shift in the future after the end constraint.
How I can set up the system?
Sorry for my bad english.
Thanks in advance.
Matteo