Hi, In earlier versions of Project has the following :
- I ask for a task A (Duration: 2 days), the transaction "Fixed Duration" and "power controlled" one.
- I would be this process, a working-resource to.
- The work for this process is set to 16h.
- If I work a second resource (Mr. Miller) would add resources for both the units to 50% - And in the view resource use can be seen that both Resources for the task 4 instead of 8 hours per day allocated were.
This works in Project 2010 no longer. Given that after adding the second resource both resources remains at 100%. But in view of the "resource deployment" is again true for both Resources 4 hours per day displayed for this operation. Is this a bug or is there a new setting, this Recalculation of the resource units activated? Please help me to solve my issue.