I'm trying to import a excel spreadsheet into project. Only need to import a few columns. Here's my problem. The first column in the xls is level 1, column 2 is level 2, column 3 is task name, column 4 is duration. Example:
PHASE Work Sub-Task Duration
PHASE 1 Clocking USB0 5
PHASE 1 Clocking USB1 2
PHASE 2 Bring up power on 3
The import wants this turned into rows..
LEVEL NAME DURATION
1 Phase 1
2 Clocking
3 USB0 5
Anyone know how to accomplish this?
Bookmarks