Hi Guys,
I am attempting to create a plan and would like MS project to realise thatall tasks cannot be completed in one day. For eg
Task1 - 4hrs
Task2 - 3 hrs
Task3 - 6 hrs
Task4 - 2 hrs
As a working day is only 8 hours long I'd expect MSP to allocate tasks 1 and 2 together on day 1 and 3 and 4 on day 2. I realise I can make each one a predecessor of the former, but I use tasks for true predessesors (ie to paint a wall the wall must be built first).
Is MSP capable of looking through a list of tasks and splitting them accordingly based on hours in the day?