My situation is that I have a huge project that requires subprojects. How do I set the predecessor of the subproject to the main project. Example:
main project:
1 task
2 task
3 task
subproject
1 task
2 task
3 task
4 task
How would I set subproject task 1 to start at the finish of main project task 3?