I am trying to go through a manual with 10 sub sections, i wanted to assign 1 hour per section maximum 3 hours per day ( i have a total of 8 hour work day)
I tried assigning a calendar to the manual review tasks which included a 3hour per day, 15 per week and 23 per months. I linked all the tasks. I expected project to start the 4th task on the next day since the first three will complete the calendar day. it put the first 8 on the given date and tasks 9 and 10 to the next date.
Help!!