Hii everybody...
I am working on EPM and Project 2007....My problem is I am putting some start date and End date to tasks and Publish the project to server...now If the resource is updating the Different Start and End date...then the End date is changing according to resource's entered date...but the start date is not getting changed....I am using Forward scheduling method...
Please help....