    I have a team which works across different time zone in
    different shifts. I want to have a calendar for my project in MS Project 2007, which can understand the timezones for my different resources What should I
    do?

  2. #2
    Join Date
    Apr 2008
    Posts
    2,139

    Re: TimeZone for Calendars in MS Project 2007

    There are four types of calendars such as base calendars, project calendars, resource calendars, and task calendars. You can modify these calendars to define the working days and hours for the entire project, for groups of resources, for individual resources, and for tasks. These calendars are distinct from the Calendar view, which shows the project schedule in a calendar format.

  3. #3
    Join Date
    May 2009
    Posts
    7

    Re: TimeZone for Calendars in MS Project 2007

    Agreed, thanks for your reply

    But my query is different

    let me give you an example:

    I have Mr. X who works in US and will work from 8:00 AM EST to 5:00 PM EST

    And I have Task 1 which has a Finish time of 1st May 09 5 PM (Please note I have my Project Server in India which has the IST time zone)

    I allocate this Task to Mr. X and being a very sincere guy he finishes his task at 5 PM EST on 1st May 09 which is 2nd May 0230 AM IST in India.

    And thereby my project will start showing me a variance right away as sson the time goes beyond 1st May 09 5 PM IST in India, now how dio I solve this

    Regards
    PS

    How will my Project Server understand

Similar Threads

  1. Can we print notes in Project 2007 or Project 2010?
    By Akau# in forum Microsoft Project
    Replies: 2
    Last Post: 26-03-2012, 06:14 PM
  2. How to open a MS project 2007 file in MS project 2010
    By pqmot in forum Windows Software
    Replies: 3
    Last Post: 30-12-2010, 04:41 PM
  3. Replies: 3
    Last Post: 10-11-2010, 07:27 PM
  4. How do I convert Project 2007 document to open in Project 2003?
    By nehal_serpa in forum Microsoft Project
    Replies: 6
    Last Post: 31-10-2007, 03:12 AM
  5. Project 2007 Client Cannot Connect To Project Server 2003
    By PARRISH in forum Microsoft Project
    Replies: 1
    Last Post: 21-02-2007, 10:24 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,998,633.85262 seconds with 17 queries