Search:

Type: Posts; User: hadjionm

Search: Search took 0.01 seconds.

  1. Replies
    9
    Views
    10,116

    Re: Using Customised Date Fields in MSP2010

    Copying and pasting the dates from Finish to Date 1, or even to Baseline Finish 10 did not work consistenly. That is, it would work OK for some tasks, but other tasks would be shown as early or late,...
  2. Re: MSP 2010 - Locking Views so Filters don't change

    OK, Found this. Ta.
  3. Re: MSP 2010 - Locking Views so Filters don't change

    Where is "Reset to default"? Can't see this.
  4. Replies
    9
    Views
    10,116

    Re: Using Customised Date Fields in MSP2010

    I am now on SP2. This formula still does not work when comparing Date1 with Finish (that is, if I copy Finish to Date1 it does not show them as being the same unless I change the view to show the...
  5. Re: MSP 2010 - Locking Views so Filters don't change

    So it seems as though MSP2010 has been changed to previous versions.

    In MSP2003 the table, group and filter saved in a view would not change on the fly, but have to be specifically changes and...
  6. Replies
    9
    Views
    10,116

    Re: Using Customised Date Fields in MSP2010

    I checked with another scheduler here. She is on "SP2 MSO 14.0.7106.5003"

    so I guess I need to be upgraded as well. Thanks for your help.
  7. MSP 2010 - Locking Views so Filters don't change

    In MSP 2010 I have an issue with filters used in views. For example, I have a view for a work update sheet which uses a particuar table and the filter "Incomplete Tasks"

    If I apply this view it...
  8. Replies
    9
    Views
    10,116

    Re: Using Customised Date Fields in MSP2010

    I can't see any reference to SP-2. Moving to SP-2 is out of my control, unfortunately. Up to our Technology Group.


    No, I am not using manual scheduling.
    As I mentioned above, DATE1 works OK...
  9. Replies
    9
    Views
    10,116

    Re: Using Customised Date Fields in MSP2010

    Hi JulieS,

    Here is the version we are using:
    Version 5.1.2600 Service Pack 3 Build 2600

    If I use, say, a Baseline Finish field in lieue of Date1 it works OK, which leads me to believe there is...
  10. Replies
    5
    Views
    1,498

    Re: Calendar month for duration vs work hours

    You need to go into the calendar options and set the weekends as working days.

    Also, in Options you can set the days/month and hours/day
  11. Re: MS Project 2010 - Set Task Finish to Always Fall on a Wednesday

    hi DashBoardDan,

    I would have a milestone task (i.e. "TASK XYZ SIGNED-OFF") to follow the work task which is dependent on it, but has its own calendar which only allows work on a Wednesday. These...
  12. Replies
    9
    Views
    10,116

    Using Customised Date Fields in MSP2010

    I am trying to convert a macro and customised text field from MSP2003 to MSP2010. The macro copies Finish to Date1. The customised text field compares Finish to Date1:
    ...
  13. Replies
    4
    Views
    1,754

    Re: MS Project 2013 problems with Windows 8

    Thanks James 911, this fixed the problem.

    I wonder why the default set up would stop you creating columns?
  14. Replies
    4
    Views
    1,754

    Re: MS Project 2013 problems with Windows 8

    Hi Expertz,

    I have reinstalled MS Project 2013 but this has not fixed the problem. I can not add new columns to a table by using the mouse to right click where I want to add it. That is, a new...
  15. Replies
    4
    Views
    1,754

    MS Project 2013 problems with Windows 8

    Hi Guys,

    I have recently upgraded to a Dell all-in-one desktop with a touch screen running Windows 8.

    I have installed Office 2013 suite of products, MS Project Professional 2013, and Visio...
  16. Re: Little dots extending past the task bar in the gantt chart?

    Thanks for the help Julie. I guess I will need to manually adjust the length of these tasks.
  17. Re: Little dots extending past the task bar in the gantt chart?

    Thanks Julie.

    Do you know whether the dots can be avoided?

    I get these dots when, for example, you have two tasks, A and B, where B is dependent on A with a FF relationship.

    If B has...
  18. Little dots extending past the task bar in the gantt chart?

    What are the little dots extending past some task bars in the gantt chart?
  19. Thread: Global.mpt

    by hadjionm
    Replies
    4
    Views
    5,194

    Re: Global.mpt

    I am also getting this problem on several files. Every time I try to run a macro I need several attempts to get past these error messages. I tried the solution you mention above, and it gets over the...
Results 1 to 19 of 19
Page generated in 1,711,637,384.12134 seconds with 13 queries