Okay, thanks. I just checked this and it works.
I have changed the calendar to the 24-hour calendar.(Tools - Change Working Time)
I also had to go to Tools - Options - Calendar and changed hours...
Type: Posts; User: Boerseun
Okay, thanks. I just checked this and it works.
I have changed the calendar to the 24-hour calendar.(Tools - Change Working Time)
I also had to go to Tools - Options - Calendar and changed hours...
Thank you JulieS and hadjionm!
Thread revival!
I am using MS Project 2007.
Still have the same problem. I have been using edays, which works, but I know it is not the right way to do it. There should be a simple way to work in...
Thread revival!
I am back to my original problem I have been using edays, but I know it is not the right way to do it. How do I create a calendar with 7 work days/week? I am using MS Project 2007.
...
I have a problem that seems to be very simple but I can't figure it out. I work in the construction industry. Our projects are based on calendar days/months, rounded to the nearest 10, so we...
Thank you Julie,
I am not planning on doing any resources on this type of schedule.
I have tried to make Saturday and Sunday work days, but it still did not work. There must be something else that...
Update on my previous post. It seems like using "elapsed days (ed)" instead of just "days" will use calendar days instead of work days.
When I have a task for one month, when I type in 30d the start...
I have the same problem. I use calendar days on my schedules, and not working days - I have now been struggling for days trying to figure it out because I know I have seen it done before.
I have...
I want to set up a schedule based on calendar days. I am sure I have seen it before, but have not been able to find it.
My project is in planning stage and I need to show for instance 30 days for...