    Re: Calendar month for duration vs work hours

    Okay, thanks. I just checked this and it works.
    I have changed the calendar to the 24-hour calendar.(Tools - Change Working Time)
    I also had to go to Tools - Options - Calendar and changed hours...
  2. Replies
    5
    Views
    1,516

    Re: Calendar month for duration vs work hours

    Thank you JulieS and hadjionm!
  3. Replies
    4
    Views
    3,165

    Re: Calendar days vs work days

    Thread revival!
    I am using MS Project 2007.
    Still have the same problem. I have been using edays, which works, but I know it is not the right way to do it. There should be a simple way to work in...
  4. Replies
    12
    Views
    28,631

    Re: Converting work days to calendar days

    Thread revival!
    I am back to my original problem I have been using edays, but I know it is not the right way to do it. How do I create a calendar with 7 work days/week? I am using MS Project 2007.
    ...
  5. Replies
    5
    Views
    1,516

    Calendar month for duration vs work hours

    I have a problem that seems to be very simple but I can't figure it out. I work in the construction industry. Our projects are based on calendar days/months, rounded to the nearest 10, so we...
  6. Replies
    12
    Views
    28,631

    Re: Converting work days to calendar days

    Thank you Julie,
    I am not planning on doing any resources on this type of schedule.
    I have tried to make Saturday and Sunday work days, but it still did not work. There must be something else that...
  7. Replies
    4
    Views
    3,165

    Re: Calendar days vs work days

    Update on my previous post. It seems like using "elapsed days (ed)" instead of just "days" will use calendar days instead of work days.
    When I have a task for one month, when I type in 30d the start...
  8. Replies
    12
    Views
    28,631

    Re: Converting work days to calendar days

    I have the same problem. I use calendar days on my schedules, and not working days - I have now been struggling for days trying to figure it out because I know I have seen it done before.
    I have...
  9. Replies
    4
    Views
    3,165

    Calendar days vs work days

    I want to set up a schedule based on calendar days. I am sure I have seen it before, but have not been able to find it.
    My project is in planning stage and I need to show for instance 30 days for...