Search:

Type: Posts; User: m_albiges

Search: Search took 0.02 seconds.

  1. MS Project 2007 issues - aggregation inconsistencies, resource names with unexplained %

    Dear all,
    I've been trying to resolve a couple of issues on MS Project 2007 - any ideas much appreciated:

    1. I've got some issues with the aggregation of some fields such as BCWS - the...
  2. Replies
    2
    Views
    1,533

    MS Project 2007 file size

    I've got a large MS Project file which I've been working on, using MS Project 2007. It's been a bit slow but working ok, but now it's over 100MB and I'm having trouble opening it. I'm wondering...
  3. Replies
    1
    Views
    1,586

    Multiple funding sources on MS Project

    Hello,
    Most of the activities in our schedule are funded from a single source so we can analyse any exceptions outside the system. However, I've been asked to see whether we could add this...
  4. Re: Maintain single (large) file or split into multiple schedules?

    ... one specific question. I understand that this will enable us to see resource usage across linked projects which is fine. But what about reporting from the linked projects - we currently do EV...
  5. Re: Maintain single (large) file or split into multiple schedules?

    Thanks Julie - that sounds like the answer. Can you suggest any links or resources that would show me how to do that step by step?

    Thanks!
    Matt.
  6. Maintain single (large) file or split into multiple schedules?

    Hi,
    My schedule is now up to around 65MB and while it still runs fine over our shared network, there are other issues such as putting it on Sharepoint or sharing by email which are limited, as well...
  7. Replies
    3
    Views
    1,542

    Re: Task costs and annualised costs

    Many thanks, Julie, works perfectly!
  8. Replies
    3
    Views
    1,542

    Task costs and annualised costs

    I've been looking to see if there is a way to show an annualised task cost within MS Project - as our budgets are annualised, it is helpful to be able to see the estimated cost, say, in the current...
  9. Replies
    7
    Views
    2,126

    Re: Earned value over time report

    Thanks for your help - I'll contact my IT department to see if they can give me any help on that one.
  10. Replies
    7
    Views
    2,126

    Re: Earned value over time report

    Many thanks Julie - that's good to know that it's not working for a reason. Interestingly though, earned value calculations are still being made based on the task costs when I open the BCWP, BCWS, SV...
  11. Replies
    7
    Views
    2,126

    Re: Earned value over time report

    I am using MS Project 2007, Service Pack 1 as well.

    Costs are assigned to tasks rather than via resources. Resources are also assigned, so if you go into the Resoucess tab of Task Information...
  12. Replies
    7
    Views
    2,126

    Earned value over time report

    I have a resourced and costed schedule for a number of projects, which has been baselined. Costs are allocated to tasks. The budget cost report works well in showing the profile of costs over the...
  13. Replies
    1
    Views
    1,032

    Data backup on MS Project

    I've developed a fairly large MS Project schedule for my department, and people are asking about how we hold/ back up the data. We've been running a large database to hold project data up to now but...
Results 1 to 13 of 13
Page generated in 1,713,982,537.20042 seconds with 13 queries