Search:

Type: Posts; User: rosscosack

Search: Search took 0.04 seconds.

  1. Replies
    3
    Views
    1,575

    Re: Hide units on RESOURCE_NAMES

    Thank you Julie, that works
  2. Replies
    3
    Views
    1,575

    Hide units on RESOURCE_NAMES

    Hi

    RE MS Project 2000
    Is it possible to hide the units on the resource_name in a task view?

    ie.
    When a task is set to fixed duration and the work is adjusted the units will also adjust. ...
  3. Replies
    1
    Views
    1,529

    Resource Reporting

    Microsoft Project 2003

    I have a project file which the summary tasks (outline level 1) are the project name. There are multiple projects (construction sites) (approx 30)
    I am doing an overhaul on...
  4. Replies
    10
    Views
    1,198

    Re: MS Project Custom Report showing Group

    Ok yeah that could work to. Although there would be a heap of button clicks to get it all formatted.

    I have the copy picture function as a back up but I wanted to use the reports module as it can...
  5. Replies
    10
    Views
    1,198

    Re: MS Project Custom Report showing Group

    Well that's interesting, a crosstab would be perfect if I could have 2 row headers eg task name and Text1. I don't suppose that is possible?

    In any case thanks for introducing me to crosstab...
  6. Replies
    10
    Views
    1,198

    Re: MS Project Custom Report showing Group

    Thanks Julie, sorry for not providing enough information, I am using project 2003 trying to group tasks by month so that the group total shows the total cost in the summary task. As I said above, I...
  7. Replies
    10
    Views
    1,198

    Re: MS Project Custom Report showing Group

    Thanks Hollyn, I am using Project 2003.
    I followed your explanation step by step and was able to create the groups.
    I am able to use custom groups when viewing on screen but I can not use the...
  8. Replies
    10
    Views
    1,198

    Re: MS Project Custom Report showing Group

    Bump, I still need help please
  9. Replies
    10
    Views
    1,198

    Re: MS Project Custom Report showing Group

    Also, I have tried setting the period but it does not show the totals.

    I want to group by month and I want it to show the totals (cost) of the group, as it does in the view
  10. Replies
    10
    Views
    1,198

    MS Project Custom Report showing Group

    Hi,

    Can I create a custom report that shows a group?

    I have been using a custom view (with custom tables, groups, filters etc), selecting the tasks and then using the copy picture function...
  11. Replies
    1
    Views
    2,650

    MS Project export to PDF via Macro

    Hello

    I have created a report which I print to .pfd and email to many resources, each resource has a report which filters to show only their tasks.
    I would like to prepare all of the reports in...
Results 1 to 11 of 11