    Baseline Time Phasing Lost??

    Tasks have been baselined. Task Usage shows hours and dates have been correctly applied to baseline. I am able to see the baseline hours spread through the months over the span of the task in the...
  2. Replies
    5
    Views
    1,875

    Re: Automatic Percent Complete?

    I am letting MS Project do the updating (f9). The percent complete rolls up to 100% when I try to enter the correct percent complete in the % Complete column... even before I "schedule" the project...
  3. Replies
    5
    Views
    1,875

    Automatic Percent Complete?

    I have inherited a MS Project 2007 file that I am busy cleaning up.

    While taking status I have found some tasks are rolling automatically to 100 percent regardless of what I enter... above a...
  4. Replies
    4
    Views
    3,112

    Re: 24 hour calendar

    That's all great food for thought James. Yeah this is an ad hoc machine testing schedule. It won't be fully integrated into the IMS. But, it will give the guys in the shop something to work with....
  5. Replies
    4
    Views
    3,112

    Re: 24 hour calendar

    OK, so I just loaded the Duration field with hours to make it easy.
  6. Replies
    4
    Views
    3,112

    24 hour calendar

    I would like to make a supplemental schedule for testing. It needs to run 24 hours and needs to have a dynamic duration field. We need to be able to manipulate the "Work" field and have the...