I have Office 2003 installed on my computer. What I am trying is to export from Project to Excel by setting up the mapping, and the preview looks good upon executing the final step, then a "Failed Operation" error message shows up. Can anyone give me some hints on what I am not doing properly? Thanks
-
Re: Export to Excel
Have you tried going to Tools >> Options >> Security and then selecting the bottom option to "Allow Legacy Format Files..."? Try that and let us know how did it go.
-
Re: Export to Excel
I was facing same problem and I'm going to try your suggestion. However, my problem happen out of the air. Suddenly, my export start giving me this problem but don't understand why? Could you share more inside regarding the cause of this problem.
Your experience and knowledge will be greatly appreciated.
-
Re: Export to Excel
I am also using PWA and tried your suggestions but my MS project does not have those options. Any other suggestion? I'm using MS Project Professional 2003.
Thanks
-
I think that you might have Service Pack 3 installed to see the legacy format options in Project Professional. The kind of issue that you are getting seems to me more like an issue with PWA than with Project.
-
Re: Export to Excel
Thanks for the help, After I installed SP3 and the problem was corrected. Thank you once again.
-
Re: Export to Excel
Thanks for the feedback and you are welcome. I am glad that you have sorted out the problem.