I am here using Microsoft Project 2007. Things are working well here but there is some issue with the default duration. The entire duration here is coming around a day and it is not at all working. I want to configure the same as per my need. But somehow it is not gteting the action task duration. It taking some default settings that comes with the software. I am annoyed with it. Does there is any option that really works and can help me to assign a task duration. Thanks.
Re: Project Professional 2007 task duration
Hi,
I'm a project manager using the MS Project 2007.
We are starting to integrate the software across our organization (we previously used 2007).
I have a similar problem involving task duration. We are set to the default of 8 hours per day, 08:00-12:00 and 13:00-17:00, and that is ok. We don't have 1/2-day or part-day tasks. all tasks are full work days.
So, the problem start when, for example, there is only 1/2 working day on a holiday. All the subsequent tasks are pushed by 1/2 day and always start at mid-day. We want to over-ride that. We want to force ALL tasks to always start at 08:00, and we will just make an exception on those holidays (of 1/2 day) to either extend the task to be 1.5 or 0 days. We never want to encounter a situation where a task starts mid-day, since it causes so many problems down the road, it took us a long time to find that this was the reason (following your great tip of adding the time of day in the view definition).
Is there any way we can solve this?
Thanks for all the help,
Dana