Hide units on RESOURCE_NAMES
Hi
RE MS Project 2000
Is it possible to hide the units on the resource_name in a task view?
ie.
When a task is set to fixed duration and the work is adjusted the units will also adjust.
When the units are 100% - there is no unit after the resource name
When the units are not 100% - there is
eg
Resource A [33%]
Thanks you
Ross
Re: Hide units on RESOURCE_NAMES
The work-around:
- Copy the resource name data into the Initials field.
- Change the Bar Style for critical and non-critical tasks to use Resource Initials instead of the Resource Name.
I hope this helps.
Re: Hide units on RESOURCE_NAMES
Thank you Julie, that works
Re: Hide units on RESOURCE_NAMES
You're welcome and thank you for the feedback.