Resource Allocation in Microsoft Project
I have an issue with the resource allocation percentage. I have made 3 tasks and assigned them to a resource. When I look at the allocation percentage then it looks like each task has a different 100%. For instance, task 1 takes 5d (40h) and has a 11% allocation that resolve to 363 hour for that month for the resource. Task 2 takes 16d (128h) and has 36% that resolves to 355 hours for that month. So, can anyone tell me how does project calculates the allocation percentage? Thanks.
re: Resource Allocation in Microsoft Project
Can you tell us what is the work for each task? A 5 day duration task with a resource assigned at 11%, should be 4.4 hours of work where, Duration x Units = Work. Or to solve units - Work/Duration or 4.4/40 = .11. A 16 day duration task with a single resource assigned at 36% = 46.08 hours. Or 46.08/128 = 0.36. I dont know why you are working with a month duration neither task duration is a month.
re: Resource Allocation in Microsoft Project
I just want to see the percentage a task takes from the resource overall time in month. For example, when a resource works for 20d in a specific month and is assigned for a task that should take 5d in that month then the allocation percentage should be 5/20 = 25%.