Re: Finish to Finish tasks
As you stated you have done finish-to-finish link, first of all you must know that it doesn’t means both A and B will finish at the same time. By doing so, it means that B cannot be finished until A. You also said that the successor tasks must start within 24 hours of the end of the predecessor. Here if A3 and B4 must finish at the same time then that constraint imposes constraints on the sum of the durations of the predecessor tasks.
Anyways, you can simply paste a link to the finish date of A3 to the finish date of A4 if you really want B4 to finish on the same date as A3. And you can do this by selecting the A3 finish date from the menu, click Finish/Copy Cell. Once done, select B4 finish date, go to Menu and select Edit/Paste Special/Paste Link.
Re: Finish to Finish tasks
That’s exactly what I wanted to know, thank you very much Big Fish. The info about pasting a finish date between tasks
is particularly useful.