MS Project 2003; Progress line in a summarybar
Hi all,
When i insert a progress line in ms project it has strange behaviour at a summary bar:
If a summary bar, for example, consists of two tasks with te following charasteristics:
Summary bar, duration 4 weeks, week 2 - week 5 (mo jan, 7th - fr feb, 1st)
Task A, duration 1 week, start week 2 (mo jan, 7th), 100% complete
Task B, duration 1 week, start week 5 (mo jan, 28th), 0 % complete
If i insert a progress line at the end of week 3 (fr jan, 18th), it 'jumpes' forward on the summary bar to the start of Task B. But i would like to have it straight trough the summary bar. How can i do this?
Thanks,
Bas
Re: MS Project 2003; Progress line in a summarybar
Re: MS Project 2003; Progress line in a summarybar
Thanks for your post, but it didn't help me.
I'm talking about the progress line, not the progress bar. The progress line is a thin red vertical line.
I don't use resources in my project.
Maybe you know also the answer to this problem.
Bye,
Bas