Re: Calendar Working Days
You can try to go to Tools >> Change Working Time. After that click and drag from the M column heading to the S column heading to select every Monday through Saturday in the entire schedule. After that edit the from: and to: as needed to show the 10 hours per day. Now you have click on the options button and edit hours per day to 10 and hours per week to 60. Hope this helps.
Re: Calendar Working Days
Thanks a lot for your help, I never knew it was that simple and what was I thinking.
Re: Calendar Working Days
Thanks for the feedback and you are most welcome. I am glad that the issue is solved for you.