Resource Usage View
I am administering a Resource Pool in Project 2010. In the resource useage view I see all my resources and underneath each the tasks that they are assigned to. Ive been asked to produce a view that shows each task and underneath each the resource names assigned to the task. Anyone know if this is possible and if so how?
-
re: Resource Usage View
Have you looked at the Task Usage view in the master project? Open the Resource Pool file and select the 3rd option. That will create a master project and if you look at the Task Usage view you should see what you are seeking -- each task and underneath each task the assignment information - represented by the name of the resource.
I hope this helps.
Julie
-
Re: Resource Usage View
Thanks for your advice JulieS. However when I look at the resource useage view in my 'Project' (not the resource pool its linked to) all I see is each resouce and underneath the the tasks they are assigned to. Same as before.
-
Re: Resource Usage View
Re-read my post -- I suggested you use the Task Usage view in a consolidate project.
Julie
-
Re: Resource Usage View
My mistake - I should be looking at the Task useage view NOT the Resource useage view shouldnt I ?! I see what I want now thanks for your help.
-
Re: Resource Usage View
Great. Glad the Task Usage view gives you what you need.
Julie