I am working with MS Project for sometime and I am not able to solve an issue. I am working in a large organization where management has argued that for planning purposes, an amount of hours is equal to a work year for example, 1800. This number is based on a formula that computes how many hours people work and how much sick time and vacation time they use and so on. The question that I am having is, how to translate this number be it 1800 or some other into the calendar? Thanks.