Can anyone tell me whether there is any utility available for implementing S-Curves in Microsoft Project 2003? Thanks for any help.
Can anyone tell me whether there is any utility available for implementing S-Curves in Microsoft Project 2003? Thanks for any help.
I have heard that Microsoft Project calculates all the ratios that are necessary to built the S-Curves. You can try to look at the earned value table: then you will see the BCWS, BCWP, ACWP. But ms project standard doesnt show the 3 curves in a graph. Anyways, it is possible to export the necessary data to Excel and build the graph in Excel, just use the "Analyse Timescale Data into Excel" button which is the Analysis toolbar.
Thank you for the information, but the problem is the field that you have told me, it will give me cost based S-Curve and I am looking for a work based timephased S-Curve. Do you have any suggestions on that? Thanks once again.
Incase you are not able to manage the resource costs, then you can try to use a fake cost such as $1/h for each resource. After that you can create the S Curves of work disguised in cost.