    Calendar month for duration vs work hours

    I have a problem that seems to be very simple but I can't figure it out. I work in the construction industry. Our projects are based on calendar days/months, rounded to the nearest 10, so we basically don't care about week-ends, 8-hour work days etc.
    A typical project will be, let's say 6-month duration, so we use 180 days, or a 1-year project will be 360 days. When I set up a schedule and enter durations for tasks it skips week-ends, so a 10 day duration ends up showing a total duration of 14 days because of the 2 week-ends in between; what I need is if a task is 10 days, I want to add 10 straight calendar days, not just work days.
    I have been using e-days, but it is not the right way to do it, it seems to be just a work-around. I am sure there must be a simple way to set the calendar to ignore work hours, week-ends etc. and just enter tasks in calendar days.

    Example, road construction:
    Task 1 - Earthworks - 30 days
    Task 2 - Road base - 20 days
    Task 3 - Curb and sidewalks - 10 days
    Task 4 - Asphalt - 10 days
    Task 5 - Closeout - 30 days
    Total project time is 100 days.

    These are calendar days, not just Monday through Friday work days. The contractor has to allow for non-workdays in his planning of the work, we don't show that on the schedule.

    Thanks!

  2. #2
    Join Date
    Dec 2006
    Posts
    489

    Re: Calendar month for duration vs work hours

    You can certainly modify the calendar to make every day a working day. However, your resources will be scheduled to work during Saturdays and Sundays.

  3. #3
    Join Date
    Mar 2009
    Location
    Melbourne, Australia
    Posts
    20

    Re: Calendar month for duration vs work hours

    You need to go into the calendar options and set the weekends as working days.

    Also, in Options you can set the days/month and hours/day

  4. #4
    Join Date
    Mar 2012
    Location
    Sarasota, Fl, USA
    Posts
    9

    Re: Calendar month for duration vs work hours

    Thank you JulieS and hadjionm!

  5. #5
    Join Date
    Mar 2012
    Location
    Sarasota, Fl, USA
    Posts
    9

    Re: Calendar month for duration vs work hours

    Okay, thanks. I just checked this and it works.
    I have changed the calendar to the 24-hour calendar.(Tools - Change Working Time)
    I also had to go to Tools - Options - Calendar and changed hours per day to 24 and hours per week to 168. I changed days per month to 0, since it would not be accurate if I select either 30 or 31. It seems like the hours per day and hours per week is able to override the 0 days per month.
    I also went to Project - Project Information to select the 24-hour calendar, and in my gant view I had to right click to select the 24-hour calendar so weeke-ends are not shown grayed out.

    Thank again!

  6. #6
    Join Date
    Dec 2006
    Posts
    489

    Re: Calendar month for duration vs work hours

    You're welcome and give yourself a pat on the back. Great rundown of all of the options settings that need to be adjusted when changing Project calendars. Kudos!

Similar Threads

  1. Is the Duration of FEAR 3 game only for 4 hours?
    By Mart^Iineau in forum Video Games
    Replies: 5
    Last Post: 23-06-2011, 09:11 PM
  2. Replies: 5
    Last Post: 23-04-2011, 10:19 PM
  3. Change Work field default to change hours, not duration?
    By Dharitree in forum Microsoft Project
    Replies: 6
    Last Post: 03-11-2009, 03:58 AM
  4. Project Duration measured in hours and minutes
    By Kuval in forum Microsoft Project
    Replies: 2
    Last Post: 09-10-2009, 02:22 PM
  5. Duration shown in days(need) to display hours
    By The Man in forum Microsoft Project
    Replies: 0
    Last Post: 23-09-2008, 05:26 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,415,071.78724 seconds with 17 queries