Dear all,
I've been trying to resolve a couple of issues on MS Project 2007 - any ideas much appreciated:
1. I've got some issues with the aggregation of some fields such as BCWS - the sub-elements add up to more than the aggregated figure at the next level up. Shouldn't they be the same?
2. I've got some unexplained % figures next to some of my resource names such as 'desiger 1 [92%]' for which there is only one resource - i.e. it should be 100%. I'm assuming that it's working this out from something, but I can't see what, and what about the remaining 8%?
Thanks!
Matt.