    MS Project 2007 issues - aggregation inconsistencies, resource names with unexplained %

    Dear all,
    I've been trying to resolve a couple of issues on MS Project 2007 - any ideas much appreciated:

    1. I've got some issues with the aggregation of some fields such as BCWS - the sub-elements add up to more than the aggregated figure at the next level up. Shouldn't they be the same?

    2. I've got some unexplained % figures next to some of my resource names such as 'desiger 1 [92%]' for which there is only one resource - i.e. it should be 100%. I'm assuming that it's working this out from something, but I can't see what, and what about the remaining 8%?

    Thanks!

    Matt.

  2. #2
    Join Date
    Dec 2006
    Posts
    489

    Re: MS Project 2007 issues - aggregation inconsistencies, resource names with unexplained %

    1. I've got some issues with the aggregation of some fields such as BCWS - the sub-elements add up to more than the aggregated figure at the next level up. Shouldn't they be the same?

    Is it possible you added new tasks or re-baselined existing tasks without rolling up the new values to the summary?

    2. I've got some unexplained % figures next to some of my resource names such as 'desiger 1 [92%]' for which there is only one resource - i.e. it should be 100%. I'm assuming that it's working this out from something, but I can't see what, and what about the remaining 8%?

    My guess is you are using either Fixed Work tasks and you increased duration, dropping the assignment units or you are using Fixed Duration tasks and you decreased work, dropping assignment units.

Similar Threads

  1. MS Project 2007 Resource Import from Excel
    By ronberrype in forum Windows Software
    Replies: 2
    Last Post: 24-03-2012, 09:08 PM
  2. Microsoft Project - Project - Trying to Show Resource Allocation
    By thisistony in forum Microsoft Project
    Replies: 2
    Last Post: 28-11-2011, 09:15 PM
  3. Resource modeling in Project 2007
    By kevinarthur_99 in forum Windows Software
    Replies: 1
    Last Post: 01-05-2011, 03:41 AM
  4. Project 2007 - Resource Calendar
    By shyman in forum Microsoft Project
    Replies: 5
    Last Post: 06-04-2010, 06:11 PM
  5. MS Project - Resource Leveling
    By ra93013 in forum Windows Software
    Replies: 3
    Last Post: 21-01-2009, 06:30 PM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,239,931.28567 seconds with 18 queries