Tasks have been baselined. Task Usage shows hours and dates have been correctly applied to baseline. I am able to see the baseline hours spread through the months over the span of the task in the matrix to the right side of Task Usage view. I opened the spreading of the hours are gone. Task Usage shows that there are hours in the baseline but they are no longer time phased. There is no spread of hours in the baseline. I am having to re-baseline each task to see the hours spread again... Has anyone heard/experienced this before?
MSP 2007