I've been looking to see if there is a way to show an annualised task cost within MS Project - as our budgets are annualised, it is helpful to be able to see the estimated cost, say, in the current financial year. We currently show full task costs (i.e. the cost over a number of years).
We can run a Budget Cost Report which breaks down costs by week so that you can look at planned cost over a given period. Is it possible to add columns into MS Project that will show you this as you update the schedule, rather than having to run the cost report each time?
Many thanks!