Hello everyone, I have a desired behavior, and can not figure out how to make project perform in this way. Basically I have a fixed work task, and when I change either the work require, or the duration required, I want project to change the units required of the resource.
I somehow got this to work for one task, but when I applied the exact same options to another, it did not work.
Any ideas?