I have a resourced and costed schedule for a number of projects, which has been baselined. Costs are allocated to tasks. The budget cost report works well in showing the profile of costs over the project. I have been updating % complete against activities and this is calculating BCWP (earned value) on the schedule. However, I am trying to run a report showing the earned value over time, but this is coming up with zeros. Any idea why?