Thread: Calendar days vs work days

  1. #1
    Join Date
    Mar 2012
    Location
    Sarasota, Fl, USA
    Posts
    9

    Calendar days vs work days

    I want to set up a schedule based on calendar days. I am sure I have seen it before, but have not been able to find it.
    My project is in planning stage and I need to show for instance 30 days for first task, 60 days for second task and 60 days for third task, which should all add up to 5 months total.
    I have tried to set it up where I make Saturday and Sunday work days, but then when I add 30 days in the Duration column, the start day and end day is not calculated to be a month apart.

    Thanks for any input...

  2. #2
    Join Date
    Mar 2012
    Location
    Sarasota, Fl, USA
    Posts
    9

    Re: Calendar days vs work days

    Update on my previous post. It seems like using "elapsed days (ed)" instead of just "days" will use calendar days instead of work days.
    When I have a task for one month, when I type in 30d the start and end days will be 1.5 months apart, but when I type in 30ed in the duration, the start and end dates are 1 month apart.

  3. #3
    Join Date
    Dec 2007
    Posts
    2,291

    Re: Calendar days vs work days

    I think that the point is that the calendar is eternal, but the durations should remain the same, unless you decide to take measures to correct this, such as increasing working hours or resources, etc. Check some similar suggestions given in this thread - Converting work days to calendar days

  4. #4
    Join Date
    Dec 2006
    Posts
    489

    Re: Calendar days vs work days

    Quote Originally Posted by Boerseun View Post
    I want to set up a schedule based on calendar days. I am sure I have seen it before, but have not been able to find it.
    My project is in planning stage and I need to show for instance 30 days for first task, 60 days for second task and 60 days for third task, which should all add up to 5 months total.
    I have tried to set it up where I make Saturday and Sunday work days, but then when I add 30 days in the Duration column, the start day and end day is not calculated to be a month apart.

    Thanks for any input...
    Hmmm. I'd say there may be an error in how you made all Saturdays and Sundays working days. Let us know what version of Project -- and we can help with detailed steps.

    Julie

  5. #5
    Join Date
    Mar 2012
    Location
    Sarasota, Fl, USA
    Posts
    9

    Re: Calendar days vs work days

    Quote Originally Posted by JulieS View Post
    Hmmm. I'd say there may be an error in how you made all Saturdays and Sundays working days. Let us know what version of Project -- and we can help with detailed steps.

    Julie
    Thread revival!
    I am using MS Project 2007.
    Still have the same problem. I have been using edays, which works, but I know it is not the right way to do it. There should be a simple way to work in calendar days vs work days.

Similar Threads

  1. Converting work days to calendar days
    By TheTurner in forum Microsoft Project
    Replies: 12
    Last Post: 02-07-2014, 10:15 PM
  2. MS Project Calendar days
    By MSPLearnerOz in forum Microsoft Project
    Replies: 5
    Last Post: 28-09-2011, 05:35 PM
  3. Replies: 3
    Last Post: 12-01-2011, 05:05 AM
  4. find period in days / hours excluding weekdays between two days?
    By Segvoia in forum Software Development
    Replies: 3
    Last Post: 19-06-2009, 11:17 AM
  5. Calendar Working Days
    By Muhammad Waqar in forum Microsoft Project
    Replies: 3
    Last Post: 18-09-2008, 02:31 AM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,711,656,037.96470 seconds with 18 queries